The Foundation of Electrical System Safety and Protection
When a fault occurs in your electrical system, thousands or even tens of thousands of amperes flow through equipment designed for hundreds of amperes under normal conditions. Can your circuit breakers interrupt these massive currents? Or will they explode trying, endangering workers and destroying equipment?
Without a short circuit analysis, you're operating on hope—not engineering. Short circuit analysis determines whether your equipment can safely handle worst-case fault conditions and forms the basis for arc flash studies, coordination analysis, and equipment selection.
Short circuit analysis is an engineering calculation that determines the maximum electrical current that can flow at every point in your power distribution system during fault conditions. The analysis calculates:
Maximum short circuit current (in kilo-amperes, or kA) at each bus, panel, switchboard, and equipment location
Comparison of calculated fault currents against the Ampere Interrupting Capacity (AIC) of installed devices
Identifies all fault current contributors including utility, generators, large motors, and UPS systems
Provides required field markings per NEC 110.24 with maximum available fault current and calculation date
For Engineers: Analysis employs symmetrical component theory using ANSI or IEC methods to calculate three-phase and line-to-ground faults. Computer modeling (SKM, ETAP, EasyPower) creates complete impedance network models considering X/R ratios, transformer impedances, conductor properties, and motor contributions.
Every circuit breaker has a maximum fault current it can safely interrupt—its AIC (Ampere Interrupting Capacity) rating. Exceed this rating, and the device can explode violently rather than clearing the fault.
According to IEEE data, 23% of facilities have at least one location where available fault current exceeds installed device ratings. These are "ticking time bombs" waiting for a fault to occur.
NEC Article 110.9 requires that equipment intended to interrupt current at fault levels shall have an interrupting rating sufficient for the available fault current.
NEC Article 110.24(A) requires service equipment to be field-marked with maximum available fault current, calculation date, and must be updated when modifications occur.
Short circuit analysis is the prerequisite for:
Scenario: Building constructed in 1985 with 480V service from 500 kVA utility transformer. Breakers rated 18-22 kA AIC—adequate for original system. In 2005, utility upgraded transformer to 1500 kVA. Nobody performed new short circuit study. Available fault current increased from 16 kA to 38 kA.
Result: Every main breaker now faces fault currents exceeding interrupting ratings. A fault could cause breaker explosion, fire, and extensive damage.
Real Cost: Replacing 40 breakers on planned schedule: $65,000
Emergency replacement after catastrophic failure: $400,000+ plus downtime
Healthcare facility added 750 kW emergency generator. Generator sized for load requirements, but nobody analyzed fault current contribution during parallel operation with utility power.
Result: During monthly generator test with utility connected, combined fault contribution exceeded main breaker AIC rating by 8 kA. Facility was one protective device away from major equipment failure.
Facility has no field-marked available fault current labels on service equipment. During insurance audit, carrier notes code violation and requires immediate remedy within 60 days or faces coverage cancellation.
Solution: Short circuit study provides PE-stamped calculations and NEC 110.24 compliant labels.
Total Timeline: 4-6 weeks for typical commercial/industrial facility. Expedited service available for urgent compliance needs.
Catastrophic breaker failure cost
Study investment
ROI preventing ONE failure
Informed Capital Planning: Phased replacement budgets vs. emergency spending (60-75% savings)
System Capacity Understanding: Determine if electrical system can support expansions
Faster Future Projects: Having fault current data accelerates arc flash and coordination studies
NEC 110.9: Interrupting Rating
Equipment must have interrupting rating sufficient for available fault current
NEC 110.24(A): Fault Current Marking
Service equipment must be field-marked with maximum fault current and date
PE Stamp Required: Calculations must be prepared by or under supervision of licensed Professional Engineer for code compliance, legal defensibility, and insurance acceptance.
Under-rated equipment is a hidden danger until the moment of truth arrives—and then it's too late.
📧 support@clarkte.com